Alta Via/Monan Way Water Main Replacement Project

A map of the Alta Via/Monan Way Construction area

  • Cost: $2,107,470
  • Funding Source: Loan and FEMA Grant
  • Start Date: May 2023
  • Estimated Completion: May 2024 
  • Location: Brookdale
  • Key elements:
    • Replacement of pipeline destroyed by CZU Lightning Complex fire
    • Larger, upgraded pipeline
    • 7 new fire hydrants

Description: The Alta Via/Monan Way Water Main Replacement Project replaces water lines in the Brookdale area that were destroyed in 2020 by the CZU Lightning Complex fire. The project installs high-strength, long-lasting iron pipe in place of polyethylene plastic that was consumed by the fire. Crews will install approximately 1,883 lineal feet of 6-inch water main and approximately 4,025 lineal feet of 8-inch main. The project also calls for replacement of associated fittings, valves and hydrants, as well as relocation or reconnection of 40 water connections. 