Zayante Drive Mainline Replacement Project

A crane lifting a section of pipe
  • Cost: $817,307
  • Funding Source: Loan
  • Start Date: October 2023
  • Completion Date: May 2024 (Awaiting final paving)
  • Location: Zayante
  • Key elements:
    • Larger, upgraded pipeline
    • 3 new fire hydrants

A map of the Zayante Mainline replacement project

A Pipeline being lowered into a trenchDescription: The Zayante Drive Mainline Replacement Project included the replacement of approximately 1,375 feet of existing 4-inch and 6-inch water pipes with new 8-inch high-strength, long-lasting iron pipe. The new water main connects at East Zayante Rd. and runs west along Zayante Dr. to the existing pump station. The project included the installation of new fire hydrants to strengthen firefighting resources.

Questions? Please contact: Zayante@slvwd.com