Redwood Park Pipeline Replacement Project
This project has been completed.
- Cost: $547,601
- Funding Source: Loan
- Start Date: May 2023
- Completion Date: June 2023 (Final paving completed September 2023)
- Location: Ben Lomond
- Key elements:
- Larger, upgraded pipeline
Description: The Redwood Park Pipeline Replacement Project included the installation of a new 8-inch water main. The new 1,260-foot pipeline, made of high-strength, long-lasting iron, replaced an existing 2-inch water main. The upgraded pipeline supports increased fire flow and water pressure at existing hydrants, which will improve vital resources for firefighters. This project was completed in preparation for the replacement of a leaking redwood tank with a new bolted steel tank.
Additional Information & Documents
- Project Background
- Initial Study and Mitigated Negative Declaration (IS-MND)
- Responses to Comments on the Draft IS-MND
- Facts, Answers, and Questions (FAQ) Summarizing Responses to Public Comments
- Mitigation Monitoring and Reporting Program (MMRP)
- Redwood Park Informational Meeting (December 8th at 5:30 pm)
- Redwood Park Tank Project Notice of Determination (NOD)